SITES: ADD TIMED GAUGING
- Open SITES under the ADDRESS MASTER DATA menu item
- Click on the "+" icon in front of the desired site to expand the view
- Choose the desired site
- Go to the Timed gauging tab at the bottom
- Click on Add
- Enter a name or title for the scheduled gauging process in the "Name" field
- Enter the Cron printout generated at www.cronmaker.com in the "Cronschedule" field (e.g. 0 0 0/1 1/1 * ? *)
- Choose the desired gauging type in the "Gauging type" field
- Activate the checkbox in the "Tank stocks" field if this option is desired
- Activate the checkbox in the "Pump totals" field if this option is desired
- Click on Save
- The "Scheduled" field is filled automatically (timed gauging order activated)
- Click on the arrow icon to return to the previous view
In CiRRUS, you can schedule time-controlled gauging processes so that they start automatically.
To set up a time-controlled gauging process, open SITES under the ADDRESS MASTER DATA menu item. You are now in the Sites view. Click on the "+" icon in front of the desired site to expand the view. Choose the desired site.
Now go to the Timed gauging tab at the bottom and click on Add. Enter the name or title of the scheduled gauging process in the "Name" field. Enter the Cron printout generated on www.cronmaker.com in the "Cronschedule" field (e.g. 0 0 0/1 1/1 * ? *). You can create printouts of your choice at www.cronmaker.com and enter them in CiRRUS. Activate the respective checkbox in the "Pump totals" and "Tank stocks" fields if the respective option is desired. Click on Save to save your entries. The "Scheduled" field is automatically filled and shows that the timed gauging order is active.
Click on the arrow icon to return to the previous view.
You now have programmed a timed gauging process which starts automatically at the set time.